RLN Centerline Engineering logo

RLN Centerline Engineering

PEC 2017 / Electrical Design v1.0

Project:

📋 Project Information

⚡ Service & Panel Parameters

🧩 Sub-panels

🔌 Connected Loads (one row = one branch circuit)

DescriptionPanelQtyWatts ea.PFPhaseDF %L (m)ConduitCont.

Phase "3" applies only when the service is 3Ø 400/230 V. Cont. = continuous load (breaker and wire at 125%).

📊 Design Summary

🧵 PEC Conduit Fill Check (Ch. 9, Tables 1 & 5)

CircuitConductorsArea mm²ConduitFillLimitStatus

Limit: 53% (1 conductor), 31% (2), 40% (over 2). The equipment ground counts as a conductor. Areas are per PEC Ch. 9 Table 4 for the selected conduit type (PVC, EMT, IMC or RSC); verify against the manufacturer's data.

✅ Design Verification & Action Guide

CheckStatusAction