SolarPlan GISRLN Centerline Engineering
Right-click the map to set site & pull NASA irradiance. Draw array area, add exclusions, place POI, trace cable.Lat - Lng -Mode: Pan
Helpdrag title to move • drag edges to resize

SolarPlan GIS — Help

Plan a solar PV plant on the map: locate the site, lay out the arrays, size the system, estimate yield and returns, and produce a client proposal. All calculations update live as you change inputs or edit the map.

Every command is in the ribbon: Home (files, search, proposal, help), Draw (array areas, exclusions, POI, cable), Design (jump to input groups, optimum tilt) and View (basemap, zoom, panels). Double-click a tab or use the arrow at the right to collapse the ribbon. This window floats: drag the title bar to move it, drag any edge or corner to resize, and keep working on the map while it is open. Switch Tooltips on or off on the Home tab for hover hints on inputs, buttons and result tiles.

1. Quick start

  1. Locate the site: type a place or lat,lng in the search box, or right-click the map. A sun marker is set and NASA POWER monthly sunshine and temperature are loaded automatically.
  2. Enter the load: in 2 Load & Solar Resource, enter monthly consumption (kWh) and your tariff.
  3. Draw the array area: choose Array Area, click each corner on the map, then press Finish shape. PV tables fill the polygon automatically.
  4. Mark obstructions: use Exclusion for trees, buildings, tanks or no-go zones; modules will avoid them.
  5. Place the POI and cable: use POI for the interconnection / inverter station, and Cable to trace the route; its length adds to cost.
  6. Choose sizing basis (section 3), review the result tiles and charts at the bottom, then press Generate Proposal.

2. Map tools

ToolHow to use
SearchPlace name (OpenStreetMap search) or coordinates such as 14.60, 121.00. The map flies there and sets the site.
Right-clickSets the site at that point and refreshes irradiance and temperature data. Do this whenever you move to a new site.
PanDefault mode. Drag to move, scroll to zoom. Clicking does nothing.
Array AreaClick vertices of the area available for panels (several areas allowed). Press Finish shape to close it (at least 3 points). The first vertex of the first area is the layout origin.
ExclusionSame as Array Area, but marks zones where no modules are placed. Any module touching one is removed.
POIOne click places the point of interconnection / inverter station. Clicking again later moves it (select POI mode first).
CableClick along the route, then Finish shape (at least 2 points). Length is measured on the ground and shown in the tooltip.
Drag nodesIn Pan mode every vertex of an array area, exclusion or cable shows a round handle. Drag it to its new location; the layout, cable length and results recalculate when you drop it. The POI marker can be dragged directly.
Finish shapeCompletes the shape being drawn. Switching tools discards an unfinished shape.
Optimum tiltFinds the tilt (0–60°) that gives the highest yearly energy for the current site data and azimuth.
BasemapSatellite (best for tracing roofs and land), Topo, or OSM street map.
List & ✕The Map objects panel lists every array, exclusion, POI and cable with a ✕ to delete it, plus layout totals (modules, area, GCR).

3. Inputs

1 Project

Name, client, location and preparer appear on the proposal. Project type tailors the whole input panel: Ground-mount shows every input; Residential rooftop and Commercial building rooftop hide inputs that do not apply (for example temperature, which loads automatically, cable cost for ground-mount, DC/AC ratio and grid CO₂ for homes) and load typical defaults for roof pitch, self-consumption and cost. Hidden inputs keep their values and still feed the calculation, and you can change any default afterwards.

2 Load & Solar Resource

Monthly billRooftop projects only. Optional: enter your monthly electricity bill and monthly use is filled in as bill ÷ tariff.
Monthly useAverage monthly electricity consumption in kWh; used for the offset percentage and the load line on the chart.
TariffGrid price per kWh that solar energy replaces.
Peak sun hoursDaily solar irradiation on a horizontal surface, kWh/m²/day (numerically the same as peak sun hours: equivalent hours per day at 1 kW/m²). Shown for every project type and reported in the results and proposal. Filled from NASA POWER when the site is set; editing it switches to your value with a typical seasonal shape.
Avg tempAverage ambient temperature in °C, for the heat-loss calculation. Also filled from NASA POWER.

3 PV Sizing

Sizing basisTarget % of consumption sizes kWp to meet the offset you enter. Use map layout capacity takes the modules that fit in your drawn areas.
Target offset %Share of annual consumption the plant should cover.
Module Wp / length / widthPanel rating and dimensions in metres (defaults: 550 Wp, 2.279 × 1.134 m).
DC/AC ratioArray kWp divided by inverter kWac (typically 1.1–1.3).

3b Battery & System Type

System typeGrid-tied: no battery; you set the self-consumed share. Hybrid: PV, battery and grid; self-use comes from the battery model. Off-grid: PV and battery only, no export; the tool reports the share of load served.
Daytime load sharePortion of consumption used while the sun is up (homes ~30–40%, offices and shops 70–85%). Night load is the rest: monthly use × (100% − this share). It is shown under the field and as the Night Load KPI.
Battery kWhNominal size. Enter 0 to auto-size to the average night load × autonomy days ÷ depth of discharge.
Depth of discharge / round-trip efficiencyUsable share of the battery and charge-discharge efficiency (about 90% each for lithium).
Battery cost / lifeCost per nominal kWh; the battery is replaced at the same cost in the year entered.
Hybrid inverter extraAdded cost of the hybrid inverter and controls as % of PV cost.

For hybrid and off-grid, tariff is the value of every kWh the PV and battery supply (for off-grid, use your avoided generator or grid cost); export rate applies to hybrid exports only.

3c Equipment & Strings

Choose a module and inverter (the presets are typical generic values, not a manufacturer's data; use Custom and type datasheet values for a real design). The tool then checks the string design and counts inverters.

Cold VocVoc × (1 + coeff × (min ambient − 25)) per module. The string's cold Voc must stay below the inverter's max DC voltage.
Hot VmpVmp at the design max cell temperature (Voc coefficient used as an approximation). It must stay above the MPPT minimum.
Modules / string0 picks the longest string that meets the voltage limits; or enter your own. Warnings appear if it breaks a limit or leaves a short last string.
InvertersThe larger of the count needed for the target DC/AC and the count needed for the MPPT inputs (strings per input limited by module Isc against the input's current limit). Actual DC/AC then sets the clipping estimate.

This is a screening check. Confirm against the datasheets, combiner and protection design, and cable voltage drop.

3d Cables & Protection

Sizes the DC string cable, the AC cable from each inverter to the POI, the AC breaker and string fusing, from the string design above.

Size selectionThe smallest standard size (4–300 mm²) that carries the design current after derating and keeps the voltage drop within the limit. AC cables may use up to 6 parallel runs.
Voltage dropResistive drop at 70 °C resistivity (copper 0.0206, aluminium 0.0339 Ω·mm²/m), operating current, DC round trip. For AC it assumes unity power factor, so reactance does not enter.
AmpacityIndicative values for XLPE copper cable on a tray (IEC 60364-5-52 style, 30 °C), reduced by your derating factor. Check them against the code tables and installation method for the project (for the Philippines, PEC 2017).
String fusesRequired when (parallel strings − 1) × Isc exceeds the module's maximum series fuse rating; then the smallest standard fuse of at least 1.5 × Isc is listed.
Cable lossesThe wiring share of Other losses should be consistent with the drops shown here; the yield is not adjusted separately.

Not covered: combiners, isolators, SPDs, earthing, short-circuit and conduit fill.

3f Farm Loads & Site

Turn Farm / seasonal loads on to replace the single monthly use with a schedule: name,kW,h/day,months,phase,start,time per load, separated by semicolons (months as 11-4 for Nov to Apr; phase 3 or 1A / 1B / 1C; start dol, ss, vfd or none; time d, n or b for day, night or both). Monthly use, daytime share, the load chart and the battery model then follow it. Design Basis & Checks adds motor starting (grid voltage dip, or inverter surge off-grid), three-phase unbalance, night peak against battery power, and ground-mount lightning exposure, fence and module height screens.

3e Transformer & MV

Adds the step-up transformer and medium-voltage connection to the results, proposal, single-line diagram and BOM, and into CAPEX and yield.

ModeAutomatic includes it when the inverter AC voltage is 600 V or more, or the plant exceeds 500 kWac. Include forces it, None connects at low voltage. Not used for off-grid.
SizingTransformer kVA = inverters per block x inverter kW ÷ grid power factor, rounded up to a standard size. Plants whose kVA is above 3150 are split into equal blocks, each with its own LV switchboard.
LV / MV ratingsLV main breaker per block, LV fault level from the transformer impedance (infinite source), MV current, MV incomer breaker (1.25 x total MV current), switchgear class (Um at least 1.1 x grid kV) and MV cable (XLPE copper or aluminium, up to 3 in parallel, 3% drop limit).
Cost and lossesCost per kVA and per metre of MV cable are placeholders: replace them with quotes. They go into CAPEX. Transformer and MV cable losses reduce the yield.

The AC cable length in 3d then runs from the inverters to the LV switchboard at the transformer; use the MV cable length for the run to the POI. Confirm relay settings, grounding, fault levels and protection with the utility.

4 Array Layout (drives the map layout)

For rooftops, set Roof type. Pitched sets modules flush to the roof (tilt = roof pitch, azimuth = the direction the roof face looks, no row gaps). Flat uses tilted racks with row spacing. Trace the roof in plan view as an Array Area, and mark roof equipment as Exclusions. Each array in the Map Tools list has its own tilt and az boxes (the grey numbers are the project values); fill them in for an array with a different orientation, such as east and west roof faces, and leave them blank to use the project values. Layout and yield then use each array's own orientation.

TiltModule tilt from horizontal.
AzimuthDirection modules face, degrees clockwise from north. 180 = south (use 0 for the southern hemisphere).
Modules highModules stacked up the slope of one table (portrait). 2 is common.
Design sun elevationSun height used to space rows so they do not shade each other. Lower values give wider spacing and fewer modules.
Edge setbackClear distance kept between modules and the area boundary (fences, access).

5 Losses

Temp coeff is the module power loss per °C above 25°C (about 0.35 for typical modules). Other losses lump soiling, wiring, mismatch, inverter efficiency and downtime (8–12% is typical). NOCT (about 45 °C) and Daytime temp uplift (daytime ambient above the 24-hour mean, about 3 °C) set the cell temperature.

6 Finance

CurrencySymbol shown on results and proposal.
Installed cost /WpTurnkey cost per watt-peak, excluding the traced cable.
Cable cost /mApplied to the traced cable length.
O&M % capex/yrYearly operating cost as a percentage of CAPEX.
Inverter repl. yr 12 %One-time replacement cost in year 12, as a percentage of PV cost (battery excluded), escalated like O&M.
DegradationYearly output decline.
EscalationYearly growth of tariff, export rate, O&M and replacement costs.
Discount rateUsed for NPV and LCOE.
LifeAnalysis period in years.
Self-consumed %Share of generation used on site (valued at tariff). The remainder is exported.
Export rateValue per kWh of exported energy.
Grid CO₂Grid emission factor in kg/kWh, for CO₂ avoided.
The default costs, tariff and export rate are placeholders. Replace them with current quotes and your utility's rates.

4. Results

The tiles at the bottom left update live:

System DC / Modules / InverterPlant size, module count and inverter capacity.
Yr-1 Energy / YieldFirst-year generation in MWh and kWh per kWp installed.
Perf. Ratio / Capacity FactorEfficiency after losses; and yearly energy divided by the plant running at full power all year.
OffsetShare of your annual consumption supplied by the plant (can exceed 100%).
CAPEX / Yr-1 SavingsTotal investment; first-year net savings after O&M.
Payback / NPV / IRRYears to recover CAPEX; present value of cash flows; and annual return rate.
LCOELifetime cost per kWh produced. Compare it with your tariff.
CO₂ avoidedTonnes per year.
Layout (kWp)Capacity of the modules that fit on the map. Compare with the target size to see whether your land is enough.

Charts: the bar chart compares monthly PV energy with your load; the line chart shows cumulative cash flow, and the payback year is where it crosses zero.

5. How it calculates

6. Files & export

Save / OpenSave asks where to put the .solar file and what to call it (Chrome, Edge and other browsers that support it). In other browsers it asks for the file name and downloads to the default folder. Open reloads it later. Save often; nothing is stored automatically.
Sample designsHome > Sample designs loads a ready-made project: Residential, Commercial, Farm or Health Clinic. Each sets the site, roof or lot, exclusions, POI, cable, equipment and finance inputs so you can see every result, the proposal, single-line diagram and BOM. The footprints are illustrative and sit on the site marker, and sun hours and costs are placeholders: move or redraw the shapes over the real roof, right-click the map to load NASA data, then replace the costs. Loading a sample replaces the current design, so Save first.
Export KMLAsks where to save and what to name the file. Array areas, exclusions, POI and cable for Google Earth or GIS software.
Generate ProposalOpens an A4 proposal: summary, to-scale layout drawing, monthly yield, financials, assumptions. Use Download PDF: it asks where to save the PDF and what to call it; changes to inputs need the proposal regenerated.

7. Tips & limits